CONSTRUCTION PROJECT UPDATES
March 15, 2004

Previous Update

ACADEMIC AND ADMINISTRATIVE BUILDINGS

Bldg 58: A new emergency eyewash station is scheduled to be installed in room 010 the afternoon of March 19th. Water to the building will be temporarily shut-off; however, occupants will be advised of the specific time, once it is determined. Contact Terri Perry at X2006, tperry@wuf.edu or Myles Sampson at X7344, msampson@uwf.edu. Contractor: Boyd Plumbing.

Bldg. 85/86 IAQ Corrections: This project involves removal of existing guttering and roof vents, sealing attic space with insulation, and reinstalling transfer grilles and gutters. Anticipate construction beginning March 29th with completion by the last week in May. Majority of work will be on exterior of building with minimal work inside. Contact Earl Smith X2001, esmith@uwf.edu, or Chuck Summers x3139, csummers@uwf.edu. Contractor: TBD.

Bldg 70 Voice Data Rewire: The work includes the premise wiring upgrade for the entire building. Construction began the second week in March and is scheduled to be complete by March 26. Contact Chuck Summers x3139, csummers@uwf.edu or Myles Sampson X7344, msampson@uwf.edu. Contractor: MCS of Tampa.

Bldg 77, ATC Lab: Modular furniture contractor is behind schedule. Completion date has been bumped up to April 7. Contact Chuck Summers x3139, csummers@uwf.edu. Contractor: ESA South

Building 207 (Gazebo near 54): Structural repairs are complete. UWF Facilities Maintenance staff will commence pressure washing and painting when weather permits. Final completion for the total project date is tentatively April 16th. Contact: Myles Sampson x7344, msampson@uwf.edu, or David Luttrell x3417, dluttrell@uwf.edu. Contractor: Toler Construction and Edwards Roofing.

Health, Leisure & Sports Facility: Erection of structural steel has started while work on concrete foundations, slabs and masonry continues; A REMINDER -Handicapped parking for the natatorium has been relocated to east of building 54 for the duration of construction. Oak Grove parking is for contractors only. Project is on schedule with project completion scheduled for January 2005. Contact David Luttrell x3417, dluttrell@uwf.edu, or Terri Perry, x2006, tperry@uwf.edu. Construction Manager: The Morette Company

International House: The IH portion of the overall facility is approximately 85% complete with interior sheet rock and other trades being installed at this time. The Japan House is approximately 90% complete, although the Garden, the Tearoom and the Tatami Room are complete. Exterior site work is being accomplished as weather permits. Substantial completion date scheduled for mid-May 2004. Contact David Luttrell x3417, dluttrell@uwf.edu or Roger Rowe x3117, rrowe@uwf.edu. Contractor: Larry Hall Construction, Inc. & Zen Associates, Inc.

CAMPUS GROUNDS, UTILITIES & MISC.:

Campus Entrance Sign, Ph I of II: Work to the sign has been completed. Facilities Management landscaping work has commenced. Final completion for the total project is tentatively scheduled for April 2nd. Contact Myles Sampson, msampson@uwf.edu, x7344 or Dave Luttrell, dluttrell@uwf.edu, x3417. Contractor: ESA South.

Chilled Water and Hot Water Piping Replacement Phase II & III: Project replaces current underground central hot and chilled water piping to buildings served by the central plant. Current work is occurring in several areas related to completing building connections to new system. To view, visit: http://uwf.edu/AEservices/aesprojects.htm. Contact Dick Walter at x2170 or rwalter@uwf.edu. Contractor: Bayou Mechanical, Inc.

Sidewalk Repairs: Project consists of replacing sections of concrete walkway across campus that present safety hazards. Anticipate construction starting date March 22 with completion by first week in May. Contact Earl Smith X2001, esmith@uwf.edu, or Myles Sampson X7344, msampson@uwf.edu.

Soccer Field Press Box and Dugouts: The press box structure is complete and the dugouts should be started next week. These wood structures are located on the south side of the Track and Soccer Field Complex. Final Inspection scheduled the week of April 15, 2004. Contact Roger E. Rowe at x3117 or rrowe@uwf.edu for more info. Contractor: Trammell Construction

Athletic Sports Complex Fencing Project: Project consists of providing new perimeter fencing around this complex to control access and vandals from damaging the various playing fields. All work should be completed by March 25, 2004. Contact Roger E. Rowe at x3117 or rrowe@uwf.edu for more info. Contractor: Tornado Fencing

Bldg 54, Planter and Sidewalk Repairs: Work has begun, and is scheduled to be completed by the end of March. Contact Chuck Summers x3139, csummers@uwf.edu. Contractor: Andrews Construction.

Parking Lot 22: PO has been issued for this project. Scheduled this week to survey the site before commencing construction. All work to be complete by March 26th Contact Chuck Summers x3139, csummers@uwf.edu or Earl Smith x 2001, esmith@uwf.edu. Contractor: Andrews Construction Co.

Building 40 Fuel Tank Replacement: This project will install a new above ground fuel storage tank for the campus heating system and remove two existing underground fuel tanks. Project is scheduled to begin in April, 2004. Contact Ron Northrup, x2040, rnorthru@uwf.edu, Contractor: Fueling Components Inc.

Barrier Gate Lots 13 & 23: A barrier gate will be constructed between lots 13 & 23 (Tennis Courts) during Spring Break. This gate will limit access between parking lots to Trolleys and other authorized vehicles. Contact Terri Perry at X2006, tperry@uwf.edu or Myles Sampson at X7344, msampson@uwf.edu.

WEST FLORIDA HISTORIC PRESERVATION, INC. PROJECTS

ACADEMIC AND HISTORICAL BUILDINGS

Village-Wide Repairs: Project underway. $334,000 to repair wood, paint and other miscellaneous repairs/restorations for the entire Pensacola Village Complex. Wescon is GC. Contact Pat Paterson x595.5985, hpaterso@uwf.edu.

ADDITIONAL NOTES:

The Project Request Form is available online at: http://uwf.edu/AEservices/aesforms.htm. Requestors will be contacted with an estimate and written Scope of Work. All renovations to space will be coordinated by a project manager and completed by outside contractors. Facilities Management focus is on preventative maintenance.

If you are buying furniture/panel systems for your office, please be aware of the accessibility to electrical and voice/data outlets. For more information regarding accessibility, please call A & E Services at x2901.

Any questions regarding these projects or unlisted projects, contact Rita Schreppel at x2938, or email: rschreppel@uwf.edu.

- Web Contacts - ADA/IDR Info - Site Index
College of Arts & Sciences - College of Business - College of Professional Studies

Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this institution by phone or in writing.

current students Student Handbook

The University of West Florida